Inside a 49-page PSU freight tender: what a forwarder actually has to quote
The lanes fit on six pages. The other forty-three decide whether the rates you put against them make money.
In August 2015, BHEL's Regional Operations Division in Mumbai invited bids for a one-year ocean freight contract: containerised imports from American and Black Sea ports into Nhava Sheva, Chennai and two inland container depots. The tender, RE/MUM/IMP/AC/IS-1512, is still on BHEL's public website. It runs to 49 pages.
The rates it asked for are long out of date, and that is not why it is worth reading. It is worth reading because it is a clean example of how a public-sector freight tender is put together: what the buyer asks you to price, what it has already priced for you, and how it decides who wins. Anyone who quotes this kind of work will recognise the shape.
What follows is a walk through it the way a pricing desk would: find the lanes, find the costs the lanes do not show, work out how the bid is scored, and note what to ask before the pre-bid meeting.
The lanes are on pages 41 to 46
The first forty pages are scope, instructions, eligibility and general terms. The part you actually put numbers into is Section V, the price bid, split into two independent bids: Price Bid A for American load ports and Price Bid B for what the tender calls the Black Sea sector. You can bid for either or both, but within a bid you must quote every line or that bid is rejected.
Each line is a load port, a discharge port, an equipment type and a projected volume. Rates are in US dollars, per container for FCL and per freight ton for LCL. Added up, there are 55 priced lines covering 621 TEU of full containers and 440 tonnes of LCL over the year.
| Bid | Discharge | FCL lines | Boxes | TEU | LCL lines | LCL tonnes |
|---|---|---|---|---|---|---|
| A, Americas | Nhava Sheva | 15 | 51 | 67 | 10 | 347 |
| A, Americas | Chennai | 10 | 240 | 374 | 3 | 40 |
| B, “Black Sea” | Nhava Sheva | 7 | 21 | 30 | 4 | 53 |
| B, “Black Sea” | Chennai | 6 | 100 | 150 | 0 | , |
| Total | 38 | 412 | 621 | 17 | 440 | |
Two things stand out before you price a single line. First, the volume is lopsided: Chennai takes 524 of the 621 TEU, and one line on its own, 40′ boxes from Long Beach to Chennai, is 54 containers. Second, the volumes are explicitly not guaranteed. The tender says the load “may increase or decrease depending upon BHEL's order book,” so the projection is a basis for scoring bids, not a commitment you can plan capacity around.
The rate is all-in, and the buyer has already priced the rest
The note under each price bid is the most expensive sentence in the document. The quoted freight “includes all charges and surcharges like BAF, CAF, GRI, ISPS, war risk charges, port congestion charges, SECA charges.” The scope repeats it: none of these will be paid separately. Whatever bunker, currency and war-risk premiums do over the contract year, the rate you bid absorbs them.
And the contract year can be longer than a year. It runs for one year, extendable by a second by mutual agreement. If you decline the extension, you must still keep working at the same rates for three more months. A Black Sea rate quoted in one market can end up applied fifteen months later.
Everything outside ocean freight, BHEL has priced itself. Terminal handling, inland haulage to the depots and delivery-order fees are paid at fixed amounts set in the tender. Meanwhile, “all the destination charges of shipping line will have to be paid by Contractor.” If the line's real charges come in above BHEL's figures, the difference comes out of your margin.
| Charge | What BHEL pays (fixed in the tender) |
|---|---|
| THC at Nhava Sheva | ₹8,450 per 20′, ₹14,585 per 40′, ₹950 per LCL freight ton |
| THC at Chennai | ₹5,750 per 20′, ₹9,344 per 40′, ₹600 per LCL freight ton |
| Haulage, Nhava Sheva ICD Mandideep | ₹42,238 per 20′, ₹68,206 per 40′ |
| Haulage, Nhava Sheva ICD Sanathnagar | ₹27,822 per 20′, ₹36,576 per 40′ |
| Delivery order | ₹4,000 per B/L |
| Hazardous surcharge | USD 150 per TEU, USD 15 per LCL freight ton |
| Container detention | Free for 21 days, then ₹3,475-₹10,250 per container per day by type |
Three more clauses carry real cost. The contractor must give 21 days free of detention at the final delivery place, ports and depots alike. Whatever free time the shipping line actually grants, the gap is yours to negotiate or absorb. Transit time is guaranteed, port by port (40 to 53 days, plus ten for depot delivery), measured from B/L date to IGM date. Each week late costs 5% of the freight on that shipment, capped at 10%. And the delivery order must be issued within two working days of receiving the original B/L. Beyond that, demurrage, ground rent and detention for the delay are recovered from your next freight bills.
None of this appears on the price bid sheet. All of it decides whether the number on the sheet was right.
How the bid is scored: one weighted total, winner takes the whole bid
Each price bid is evaluated as a single number: every rate multiplied by its projected volume, summed into a “total cash flow.” After a reverse auction among technically qualified bidders, the lowest total, the L1 bidder, gets the entire load for that bid. There is no lane-by-lane split.
That makes the volume column as important as the rate column. A dollar off the 54-container Long Beach-Chennai line moves your total 54 times as much as a dollar off a one-container line from Santos. Lines with a single box still have to be quoted, and quoted sensibly, but the bid is won or lost on the handful of heavy lanes, nearly all of them into Chennai.
Two details shape the auction. Rates you reduce in the reverse auction must come down pro-rata against your sealed bid, so the shape of your sealed rates carries through to the end. And currency is fixed at two different moments. Bids are compared at SBI's TT selling rate on the technical bid opening date, but you are paid in rupees at the rate on each B/L date. Over a year, that gap is a currency position you are carrying whether you meant to or not.
Read it like a checker, not a reader
Long tenders are assembled from earlier tenders, and the seams show. In this one, Section I says BHEL imports from “various ports of Europe & Middle East Sector,” while the title and price bids say America and Black Sea. Price Bid B is headed Black Sea, but its ports include Helsinki and Koper, which are on the Baltic and the Adriatic, and its total line describes cargo “from Europe to Nhava Sheva” even though six of its lines go to Chennai. Haulage rates and payment terms are listed for an ICD at Bangalore that is not among the stated discharge points. Chicago, an inland city, appears as a load port.
None of these is unusual, and none is a reason not to bid. Each is a question worth sending in writing before the pre-bid meeting, because the answer can change your routing or your cost. Once bids are open, the tender is explicit that no modification will be entertained.
Check eligibility before spending a week on pricing. This tender required an average ocean-freight turnover of at least ₹1.6 crore over three years, completed freight contracts of set minimum values in the last seven years, a ₹75 lakh bank solvency certificate, a ₹2 lakh earnest money deposit, and a Class III digital signature to use the e-procurement portal at all. A smaller forwarder may need a partner to qualify.
What changes when you price the next one
Build the lane table before anything else. Pull every priced line into one sheet: load port, discharge port, equipment, volume, transit commitment. It is the only way to see where the weight sits and which lines need carrier quotes first.
Price the weight, not the list. Sort by volume. Get your sharpest buy rates on the heaviest lanes, and make sure the single-box lines are covered without spending your best hours on them.
Cost every fixed charge against reality.Put the buyer's THC, haulage, DO and free-time figures next to what the line will actually charge you. The difference, multiplied by the volume, is a cost that belongs in your freight rate.
Price the surcharge and currency risk explicitly. An all-in rate held for up to fifteen months, paid at a different exchange rate from the one it was scored at, needs a buffer you have decided on, not one you hope you left.
Send your questions early. Every inconsistency you find is cheaper to resolve before the pre-bid meeting than after the award.